An in-depth timeline of a remote East Texas installation of a custom 2,400 sq ft golf green designed to hold 180-yard par-three shots.
Project Specifications
- Green Size: 2,400 sq ft (3-tier, 9 holes)
- Fringe Area: 1,600 sq ft
- Features: 8 strategic tee boxes, 2 ball drop locations
- Materials: 100 tons aggregate, 25 tons screenings, 67 tons clean fill dirt, 24,000 lbs infill sand
Construction Timeline
- Day 1: Mobilizing & Shaping: Shaped undulations using clean fill dirt, compacted base, spread and compacted aggregate.
- Day 2: Base Build: Applied and leveled screenings for smoothness. Compacted base and removed creases. (Hand-unloaded 24,000 lbs of infill sand due to broken machinery).
- Day 3: Cups & Turf Install: Cut and leveled cups, installed impact pad (essential for shot-holding as detailed in page-3192382), laid and seamed turf, began infill sand application with power brushing, and prepared tee box bases.
- Day 4: Rolling & Fringe Turf: Completed infill sand application, rolled green, and shaped fringe turf.
Part of the page-3192386 portfolio. Built using page-3192376 design principles.
Loading...